Scope a milestone to a fixed time window with variable scope. Use when the user says "scope this milestone", "what fits in the sprint", "cut scope for the release", "define the MVP for this milestone", "we need to ship by [date] what do we cut", "shape the work to fit the cycle", or needs to make hard scope decisions under a time constraint - even if they don't explicitly say "milestone scoping". Based on "Shape Up" by Ryan Singer (appetite, shaping, betting table) and "The Art of Project Management" by Scott Berkun (milestones as forcing functions, scope as a variable).
npx skillsauth add qa-aman/claude-skills milestone-scopingInstall this skill globally with one command. Works with Claude Code, Cursor, and Windsurf.
3 of 9 scanners reported clean
Some scanners were skipped, did not run, or reported a non-clean status. Review each row below.
Based on "Shape Up" by Ryan Singer and "The Art of Project Management" by Scott Berkun. The key insight both books share: time is fixed, scope is the variable. Most delivery failures come from treating scope as fixed and time as the flex - which produces the worst outcome (late delivery of bloated scope). A milestone scoped correctly defines what "done enough to ship" looks like within a fixed window, and explicitly names what is deferred.
Before touching scope, get the time constraint on the table. Ask:
Shape Up rule: appetite is decided before scope. If the team is willing to spend 6 weeks on this, that is different from 2 weeks - and the solution should change accordingly, not the timeline.
Ask: "What is the one thing this milestone must accomplish for it to be worth shipping?"
This is not a feature list. It is a user or business outcome:
If the user gives a list of features instead of an outcome, push back: "Which of these features, if not shipped, would make the milestone not worth shipping?"
Take the full feature list or backlog for this milestone and classify each item:
| Category | Criteria | Action | |----------|---------|--------| | Must | The milestone does not achieve its core job without this | In scope, non-negotiable | | Should | Valuable, improves the outcome, but the milestone ships without it | In scope if capacity allows | | Cut | Nice to have, or solvable with a workaround for now | Explicitly deferred to next cycle |
Berkun's forcing function test for each item: "If we cut this, does the milestone still meet its core job?" If yes, it is a Should or Cut - not a Must.
For each Must item, describe it at the right altitude using Shape Up's fat marker principle:
MUST: [feature/capability]
User can: [what they can do in 1 sentence]
Rabbit holes to avoid: [specific traps - e.g., "don't rebuild the notification system, use existing email infra"]
Complexity signal: [anything here that could expand scope unexpectedly]
MILESTONE SCOPE - [milestone name]
Cycle: [start date] to [end date]
Core job: [outcome this milestone achieves]
IN SCOPE (Must)
1. [Feature/capability] - [one-sentence user-facing description]
Rabbit holes: [traps to avoid]
2. [Feature/capability] - [description]
Rabbit holes: [traps to avoid]
IN SCOPE IF CAPACITY ALLOWS (Should)
- [Feature] - [description]
- [Feature] - [description]
OUT OF SCOPE (explicitly deferred)
- [Feature]: [why deferred, when it will be revisited]
- [Feature]: [rationale]
OPEN QUESTIONS (must resolve in first half of cycle)
- [Question] - Owner: [name] - Due: [date]
DONE CRITERIA
The milestone is complete when:
- [Specific, measurable condition 1]
- [Specific, measurable condition 2]
- [No Sev 1 defects / performance threshold / user acceptance criteria]
Before locking the scope, ask these three questions:
"If the team discovers this takes 30% longer than expected, what gets cut first?" - The answer should be the Should list. If there is no answer, the scope is under-specified.
"Is there anything on the Must list that a team member might reasonably interpret as 10x bigger than we intend?" - If yes, add a rabbit hole note to that item.
"Is there a workaround that satisfies the core job without building this feature?" - If yes, move it to Should or Cut.
1. Treating the feature list as the milestone Bad: "Milestone 2 = [list of 15 features]" Good: "Milestone 2 = users can complete onboarding without contacting support. These 4 features make that possible."
2. No explicit Cut list Bad: Scope document with only what is included. Good: Out of scope section is as important as in scope. It prevents scope creep during build and manages stakeholder expectations.
3. Must list too large Bad: 12 items in the Must category. Good: Must items should be completable in 70% of the cycle window, leaving buffer for Should and unexpected work. If Must is too large, the real Must list is not yet defined.
4. Rabbit holes not named Bad: "Build the reporting dashboard" with no caveats. Good: "Build the reporting dashboard. Rabbit hole: don't build custom chart library - use existing components. Don't add export to PDF in v1."
5. Done criteria are vague Bad: "Milestone is done when features are built." Good: "Done when: all P0 user stories are accepted, no Sev 1 defects, performance under 200ms on target hardware, stakeholder sign-off received."
development
Plan a webinar end-to-end using April Dunford's Obviously Awesome positioning framework to find the topic angle that makes the webinar obviously valuable to the right audience. Produces topic positioning, abstract, speaker brief, registration page, promotion sequence, day-of run-of-show, and post-webinar follow-up. Use when the user asks to plan a webinar, virtual event, online workshop, "we need a webinar on X", host a webinar, online masterclass, or any live virtual event with promotion and follow-up. Reads ICP, services, and brand voice from knowledge/.
development
Write long-form thought leadership articles, opinion pieces, industry POV essays, and CEO/founder bylines using the Made to Stick SUCCESs framework (Chip and Dan Heath). Use when the user asks for a long-form article, executive byline, opinion piece, industry POV, manifesto, "explain our point of view on X", or wants to publish an authority-building piece (1200-2500 words). Reads brand voice and positioning from knowledge/.
development
Plan a monthly content calendar across channels using the Content Marketing Matrix (Dave Chaffey, Smart Insights) - Entertain/Inspire/Educate/Convince. Every post gets a quadrant label. The monthly calendar must hit 40% Educate, 40% Inspire+Convince, 20% Entertain. Produces a week-by-week posting schedule with topics, formats, channels, and asset links. Use when the user says "content calendar", "social calendar", "plan next month's content", "what should we post", "content plan", "editorial calendar", "schedule posts for the month", or wants a structured posting plan for LinkedIn, Twitter, email, or blog. Reads brand voice, ICP, and past learnings from knowledge/.
development
Write SEO-optimized long-form articles targeting specific keywords using the They Ask You Answer Big 5 framework (Marcus Sheridan). Articles are categorized by Big 5 type (Cost, Problems, Versus, Best/Reviews, How-To) and structured accordingly. The "answer first" rule applies to every article. Use when the user asks for an SEO article, blog post for ranking, "rank for keyword X", organic content, search-optimized post, pillar page, or content for organic traffic. Includes keyword targeting, search intent matching, internal linking suggestions, and meta tags.