Risk analysis using risk registers, probability/impact matrices, and mitigation planning. Identifies, assesses, and manages project, business, and technical risks with structured response strategies.
npx skillsauth add prorise-cool/claude-code-multi-agent risk-analysisInstall this skill globally with one command. Works with Claude Code, Cursor, and Windsurf.
3 of 9 scanners reported clean
Some scanners were skipped, did not run, or reported a non-clean status. Review each row below.
Use this skill when:
Systematically identify, assess, and manage risks using risk registers, probability/impact matrices, and structured response planning. Supports project risks, business risks, technical risks, and opportunity management.
Risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on objectives. Risk analysis involves:
| Concept | Definition | Action | |---------|------------|--------| | Risk | Potential future event (uncertain) | Plan response | | Issue | Current problem (certain) | Resolve now |
| Type | Effect | Response Goal | |------|--------|---------------| | Threat | Negative impact | Minimize exposure | | Opportunity | Positive impact | Maximize benefit |
The central repository for all identified risks:
## Risk Register
| ID | Risk Description | Category | Probability | Impact | Score | Owner | Response | Status |
|----|-----------------|----------|-------------|--------|-------|-------|----------|--------|
| R-001 | [Description] | [Category] | H/M/L | H/M/L | [P×I] | [Name] | [Strategy] | Open |
| Field | Description | |-------|-------------| | ID | Unique identifier | | Description | Clear risk statement | | Category | Type of risk | | Probability | Likelihood of occurrence | | Impact | Consequence if it occurs | | Score | Risk priority (P × I) | | Owner | Person responsible | | Response | Planned response strategy | | Status | Open, Mitigated, Closed, Occurred |
| Category | Examples | |----------|----------| | Technical | Technology failure, integration issues | | Schedule | Delays, dependencies | | Cost | Budget overrun, resource costs | | Resource | Skill gaps, availability | | External | Vendor, regulatory, market | | Organizational | Change resistance, priorities | | Quality | Defects, performance | | Security | Data breach, unauthorized access |
Probability Scale:
| Level | Score | Description | Likelihood | |-------|-------|-------------|------------| | Very Low | 1 | Rare | < 10% | | Low | 2 | Unlikely | 10-30% | | Medium | 3 | Possible | 30-50% | | High | 4 | Likely | 50-70% | | Very High | 5 | Almost Certain | > 70% |
Impact Scale:
| Level | Score | Schedule | Cost | Quality | |-------|-------|----------|------|---------| | Very Low | 1 | < 1 week | < 5% | Minor | | Low | 2 | 1-2 weeks | 5-10% | Noticeable | | Medium | 3 | 2-4 weeks | 10-20% | Significant | | High | 4 | 1-3 months | 20-40% | Major | | Very High | 5 | > 3 months | > 40% | Critical |
Risk Score = Probability × Impact
Score Range: 1-25
Risk Priority Zones:
| Score | Priority | Action | |-------|----------|--------| | 1-4 | Low | Accept or monitor | | 5-9 | Medium | Active management | | 10-14 | High | Priority attention | | 15-25 | Critical | Immediate action |
quadrantChart
title Risk Matrix
x-axis Low Impact --> High Impact
y-axis Low Probability --> High Probability
quadrant-1 Critical
quadrant-2 High Priority
quadrant-3 Low Priority
quadrant-4 Medium Priority
| Strategy | Description | When to Use | |----------|-------------|-------------| | Avoid | Eliminate the threat | High probability and impact | | Transfer | Shift to third party | Financial/contractual risks | | Mitigate | Reduce probability or impact | Most common approach | | Accept | Acknowledge, no action | Low priority risks |
| Strategy | Description | When to Use | |----------|-------------|-------------| | Exploit | Ensure opportunity occurs | High-value opportunities | | Share | Partner to increase capability | Need external help | | Enhance | Increase probability or impact | Moderate opportunities | | Accept | Take advantage if it occurs | Low-effort opportunities |
## Risk Response Plan: R-001
**Risk:** [Description]
**Strategy:** [Avoid/Transfer/Mitigate/Accept]
### Prevention Actions
| Action | Owner | Due Date | Status |
|--------|-------|----------|--------|
| [Preventive measure] | [Name] | [Date] | [Status] |
### Contingency Plan
**Trigger:** [What indicates risk is occurring]
**Actions:**
1. [Contingency action 1]
2. [Contingency action 2]
### Residual Risk
**After mitigation:**
- Probability: [Reduced level]
- Impact: [Reduced level]
- New Score: [Residual score]
Sources for risk identification:
Techniques:
Risk statement format:
"There is a risk that [CONDITION/CAUSE] may result in [CONSEQUENCE/IMPACT]"
Example:
"There is a risk that key developer leaves may result in schedule delay and knowledge loss"
For each risk:
For each risk:
## Risk Assessment Summary
| ID | Risk | P | I | Score | Priority |
|----|------|---|---|-------|----------|
| R-001 | [Risk 1] | 4 | 5 | 20 | Critical |
| R-002 | [Risk 2] | 3 | 3 | 9 | Medium |
| R-003 | [Risk 3] | 2 | 2 | 4 | Low |
For each significant risk:
After planned mitigations:
Regular review cadence:
## Risk Register: [Project/Initiative]
**Date:** [ISO Date]
**Owner:** [Name]
**Review Cycle:** [Weekly/Monthly]
| ID | Risk Description | Category | P | I | Score | Owner | Response | Actions | Status |
|----|-----------------|----------|---|---|-------|-------|----------|---------|--------|
| R-001 | Key developer may leave during critical phase | Resource | 4 | 5 | 20 | PM | Mitigate | Cross-train, document | Open |
| R-002 | Third-party API may have breaking changes | Technical | 3 | 4 | 12 | Tech Lead | Mitigate | Abstraction layer | Open |
| R-003 | Budget approval may be delayed | Cost | 2 | 4 | 8 | Sponsor | Accept | Monitor | Open |
| R-004 | New regulation may require features | External | 2 | 3 | 6 | BA | Accept | Watch | Open |
### Summary
- **Total Risks:** 4
- **Critical (15+):** 1
- **High (10-14):** 1
- **Medium (5-9):** 1
- **Low (1-4):** 1
quadrantChart
title Risk Assessment Matrix
x-axis Low Impact --> High Impact
y-axis Low Probability --> High Probability
quadrant-1 Critical - Immediate Action
quadrant-2 High - Active Management
quadrant-3 Low - Monitor
quadrant-4 Medium - Plan Response
"R-001 Key Dev": [0.9, 0.8]
"R-002 API Changes": [0.7, 0.6]
"R-003 Budget": [0.7, 0.35]
"R-004 Regulation": [0.5, 0.35]
risk_register:
name: "[Project/Initiative]"
version: "1.0"
date: "2025-01-15"
owner: "Project Manager"
review_cycle: "weekly"
risk_appetite:
overall: "moderate"
schedule: "low"
cost: "moderate"
quality: "low"
scales:
probability:
1: "Rare (<10%)"
2: "Unlikely (10-30%)"
3: "Possible (30-50%)"
4: "Likely (50-70%)"
5: "Almost Certain (>70%)"
impact:
1: "Very Low"
2: "Low"
3: "Medium"
4: "High"
5: "Very High"
risks:
- id: "R-001"
description: "Key developer may leave during critical phase"
category: "Resource"
probability: 4
impact: 5
score: 20
priority: "critical"
owner: "Project Manager"
response_strategy: "mitigate"
response_actions:
- action: "Cross-train team member"
owner: "Tech Lead"
due_date: "2025-02-01"
status: "in_progress"
- action: "Document critical knowledge"
owner: "Developer"
due_date: "2025-02-15"
status: "not_started"
contingency:
trigger: "Developer gives notice"
actions:
- "Accelerate knowledge transfer"
- "Engage contractor"
residual_risk:
probability: 3
impact: 3
score: 9
status: "open"
created_date: "2025-01-15"
last_reviewed: "2025-01-15"
summary:
total: 4
by_priority:
critical: 1
high: 1
medium: 1
low: 1
by_status:
open: 4
mitigated: 0
closed: 0
occurred: 0
## Risk Assessment Summary
**Project:** [Name]
**Date:** [ISO Date]
**Assessed By:** risk-analyst
### Risk Profile
| Priority | Count | Top Risk |
|----------|-------|----------|
| Critical | 1 | Key developer leaving |
| High | 1 | Third-party API changes |
| Medium | 1 | Budget approval delay |
| Low | 1 | Regulatory changes |
### Critical Risks Requiring Action
#### R-001: Key Developer Departure
- **Score:** 20 (P:4 × I:5)
- **Response:** Mitigate through cross-training and documentation
- **Target Residual:** 9 (P:3 × I:3)
- **Actions:** 2 in progress, 0 completed
### Risk Trends
| Metric | This Period | Last Period | Trend |
|--------|-------------|-------------|-------|
| Total Risks | 4 | 3 | ↑ |
| Critical | 1 | 0 | ↑ |
| Closed | 0 | 1 | ↓ |
### Recommendations
1. **Immediate:** Accelerate R-001 mitigation actions
2. **This Week:** Complete API abstraction layer design
3. **Monitor:** Watch for regulatory announcements
| Pitfall | Prevention | |---------|------------| | Vague risk descriptions | Use "condition may cause consequence" format | | Inconsistent scoring | Define and use standard scales | | No risk owners | Assign owner at identification | | Stale register | Schedule regular reviews | | Ignoring opportunities | Include positive risks | | Over-analysis | Focus on high-priority risks | | No contingency | Plan for when risks occur |
swot-pestle-analysis - Strategic threats/opportunitiesroot-cause-analysis - When risks occurdecision-analysis - Risk-based decisionsprioritization - Risk prioritizationdevelopment
使用 Playwright 与本地 Web 应用程序交互和测试的工具包。支持验证前端功能、调试 UI 行为、捕获浏览器截图和查看浏览器日志。
testing
Plan user research studies - method selection, participant recruitment, study design, and research questions for generative and evaluative research.
development
Design and plan usability tests - task creation, think-aloud protocols, moderator scripts, metrics definition, and analysis frameworks.
content-media
Create service blueprints - frontstage/backstage visualization, touchpoints, support processes, evidence, and service design methodology.