Build and maintain a project or product risk register. Use when asked to create a risk register, identify project risks, build a risk matrix, or document risks and mitigations for a programme. Produces a complete risk register with likelihood/impact scoring, RAG status, ownership, and prioritised mitigations.
npx skillsauth add mohitagw15856/pm-claude-skills risk-registerInstall this skill globally with one command. Works with Claude Code, Cursor, and Windsurf.
3 of 9 scanners reported clean
Some scanners were skipped, did not run, or reported a non-clean status. Review each row below.
This skill produces a complete risk register for a project, programme, or product. Output follows standard risk management practice with likelihood × impact scoring, RAG status, a risk heat map, and specific mitigation and contingency plans. Ready to share with a project board, steering committee, or programme office.
Ask the user for these if not provided:
Project stage: [Discovery / Delivery / Launch / Live / Programme] Version: [1.0] Owner: [PM / Programme Manager / Risk Lead] Last reviewed: [Date] Next review: [Date — recommend weekly during delivery, monthly during discovery] Status: [Active / Archived]
Likelihood (L)
| Score | Label | Definition | |---|---|---| | 5 | Almost certain | >80% probability of occurring | | 4 | Likely | 60–80% probability | | 3 | Possible | 40–60% probability | | 2 | Unlikely | 20–40% probability | | 1 | Rare | <20% probability |
Impact (I)
| Score | Label | Definition | |---|---|---| | 5 | Critical | Programme failure, regulatory breach, major financial loss, safety event | | 4 | High | Significant schedule delay (>4 weeks), scope reduction, reputational damage | | 3 | Medium | Moderate delay (1–4 weeks), cost overrun, reduced quality | | 2 | Low | Minor delay (<1 week), manageable cost increase | | 1 | Negligible | Minimal impact, easily absorbed |
Risk Score = L × I
| Score | RAG | Action | |---|---|---| | 20–25 | 🔴 Critical | Immediate escalation; active management required | | 12–19 | 🔴 High | Owner-assigned mitigation; weekly review | | 8–11 | 🟡 Medium | Mitigation planned; fortnightly review | | 4–7 | 🟡 Low | Monitor; monthly review | | 1–3 | 🟢 Negligible | Accept; review if context changes |
| ID | Risk | Category | L | I | Score | RAG | Owner | Status | Mitigation | Contingency | Review date | |---|---|---|---|---|---|---|---|---|---|---|---| | R01 | [Risk description — be specific: "Third-party API may not support required volume, causing X to fail"] | [Schedule / Technical / Resource / Commercial / Compliance / External] | [1–5] | [1–5] | [L×I] | 🔴/🟡/🟢 | [Name] | [Open / Mitigating / Closed] | [What are we doing to reduce likelihood or impact?] | [What do we do if it happens?] | [Date] | | R02 | [...] | [...] | [...] | [...] | [...] | [...] | [...] | [...] | [...] | [...] | [...] |
Use these to prompt risk identification. Add, remove, or customise for your project.
Plot risks by likelihood (Y axis) and impact (X axis):
│ Low Medium High Critical
│ (1) (2-3) (4) (5)
─────────┼────────────────────────────────────
Almost │ 🟡 🟡 🔴 🔴
certain │
(5) │
─────────┼────────────────────────────────────
Likely │ 🟡 🟡 🔴 🔴
(4) │
─────────┼────────────────────────────────────
Possible │ 🟢 🟡 🟡 🔴
(3) │
─────────┼────────────────────────────────────
Unlikely │ 🟢 🟢 🟡 🟡
(2) │
─────────┼────────────────────────────────────
Rare │ 🟢 🟢 🟢 🟡
(1) │
[Plot each risk ID on this grid — e.g. R01 lands at L4/I5 = 🔴 Critical]
For steering committee or board-level reporting:
| Rank | Risk | Score | RAG | Owner | Mitigation status | |---|---|---|---|---|---| | 1 | [Most critical risk — plain English description] | [X] | 🔴 | [Owner] | [Active / Planned / Not started] | | 2 | [...] | [...] | 🔴 | [...] | [...] | | 3 | [...] | [...] | 🟡 | [...] | [...] | | 4 | [...] | [...] | 🟡 | [...] | [...] | | 5 | [...] | [...] | 🟡 | [...] | [...] |
Decisions required from steering:
| Risk ID | Change | Detail | |---|---|---| | [R03] | Score increased | [L moved from 2 → 4 — vendor confirmed delay in API availability] | | [R07] | Risk closed | [Legal sign-off received on 12 May] | | [NEW] | New risk identified | [R09 — budget freeze announcement affects Phase 2 funding] |
A risk is closed when:
Issues log: [Link to issues log — risks that have materialised and are now active problems being managed]
development
Build a framework for creating shareable, high-reach social media content. Use when asked to plan viral content, develop a shareable content strategy, create a hook writing system, or build a repeatable process for content that gets shared. Produces a platform-specific viral content framework with hook formulas, content structures, shareability triggers, and a content testing system.
development
Generate article or newsletter thumbnail candidates using the Gemini API from inside Claude Code. Claude reads article copy, proposes composition concepts, writes image generation prompts incorporating brand specs, calls Gemini to generate the images, evaluates the results via computer vision, and returns ranked candidates with rationale. Use when asked to create thumbnails, generate cover images, or produce visual candidates for an article or newsletter.
testing
Flips Claude's default from "find reasons you're right" to "find reasons you're wrong." A genuine thinking partner, not a mirror with grammar. Use before high-stakes decisions, plans, assumptions, or pitches you haven't stress-tested.
development
Scrapes a Substack Notes page and exports engagement data (likes, comments, restacks) to a formatted .xlsx file with conditional formatting and summary stats.