plugins/business-analysis/skills/risk-analysis/SKILL.md
Risk analysis using risk registers, probability/impact matrices, and mitigation planning. Identifies, assesses, and manages project, business, and technical risks with structured response strategies.
npx skillsauth add melodic-software/claude-code-plugins risk-analysisInstall this skill globally with one command. Works with Claude Code, Cursor, and Windsurf.
3 of 9 scanners reported clean
Some scanners were skipped, did not run, or reported a non-clean status. Review each row below.
Use this skill when:
Systematically identify, assess, and manage risks using risk registers, probability/impact matrices, and structured response planning. Supports project risks, business risks, technical risks, and opportunity management.
Risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on objectives. Risk analysis involves:
| Concept | Definition | Action | |---------|------------|--------| | Risk | Potential future event (uncertain) | Plan response | | Issue | Current problem (certain) | Resolve now |
| Type | Effect | Response Goal | |------|--------|---------------| | Threat | Negative impact | Minimize exposure | | Opportunity | Positive impact | Maximize benefit |
The central repository for all identified risks:
## Risk Register
| ID | Risk Description | Category | Probability | Impact | Score | Owner | Response | Status |
|----|-----------------|----------|-------------|--------|-------|-------|----------|--------|
| R-001 | [Description] | [Category] | H/M/L | H/M/L | [P×I] | [Name] | [Strategy] | Open |
| Field | Description | |-------|-------------| | ID | Unique identifier | | Description | Clear risk statement | | Category | Type of risk | | Probability | Likelihood of occurrence | | Impact | Consequence if it occurs | | Score | Risk priority (P × I) | | Owner | Person responsible | | Response | Planned response strategy | | Status | Open, Mitigated, Closed, Occurred |
| Category | Examples | |----------|----------| | Technical | Technology failure, integration issues | | Schedule | Delays, dependencies | | Cost | Budget overrun, resource costs | | Resource | Skill gaps, availability | | External | Vendor, regulatory, market | | Organizational | Change resistance, priorities | | Quality | Defects, performance | | Security | Data breach, unauthorized access |
Probability Scale:
| Level | Score | Description | Likelihood | |-------|-------|-------------|------------| | Very Low | 1 | Rare | < 10% | | Low | 2 | Unlikely | 10-30% | | Medium | 3 | Possible | 30-50% | | High | 4 | Likely | 50-70% | | Very High | 5 | Almost Certain | > 70% |
Impact Scale:
| Level | Score | Schedule | Cost | Quality | |-------|-------|----------|------|---------| | Very Low | 1 | < 1 week | < 5% | Minor | | Low | 2 | 1-2 weeks | 5-10% | Noticeable | | Medium | 3 | 2-4 weeks | 10-20% | Significant | | High | 4 | 1-3 months | 20-40% | Major | | Very High | 5 | > 3 months | > 40% | Critical |
Risk Score = Probability × Impact
Score Range: 1-25
Risk Priority Zones:
| Score | Priority | Action | |-------|----------|--------| | 1-4 | Low | Accept or monitor | | 5-9 | Medium | Active management | | 10-14 | High | Priority attention | | 15-25 | Critical | Immediate action |
quadrantChart
title Risk Matrix
x-axis Low Impact --> High Impact
y-axis Low Probability --> High Probability
quadrant-1 Critical
quadrant-2 High Priority
quadrant-3 Low Priority
quadrant-4 Medium Priority
| Strategy | Description | When to Use | |----------|-------------|-------------| | Avoid | Eliminate the threat | High probability and impact | | Transfer | Shift to third party | Financial/contractual risks | | Mitigate | Reduce probability or impact | Most common approach | | Accept | Acknowledge, no action | Low priority risks |
| Strategy | Description | When to Use | |----------|-------------|-------------| | Exploit | Ensure opportunity occurs | High-value opportunities | | Share | Partner to increase capability | Need external help | | Enhance | Increase probability or impact | Moderate opportunities | | Accept | Take advantage if it occurs | Low-effort opportunities |
## Risk Response Plan: R-001
**Risk:** [Description]
**Strategy:** [Avoid/Transfer/Mitigate/Accept]
### Prevention Actions
| Action | Owner | Due Date | Status |
|--------|-------|----------|--------|
| [Preventive measure] | [Name] | [Date] | [Status] |
### Contingency Plan
**Trigger:** [What indicates risk is occurring]
**Actions:**
1. [Contingency action 1]
2. [Contingency action 2]
### Residual Risk
**After mitigation:**
- Probability: [Reduced level]
- Impact: [Reduced level]
- New Score: [Residual score]
Sources for risk identification:
Techniques:
Risk statement format:
"There is a risk that [CONDITION/CAUSE] may result in [CONSEQUENCE/IMPACT]"
Example:
"There is a risk that key developer leaves may result in schedule delay and knowledge loss"
For each risk:
For each risk:
## Risk Assessment Summary
| ID | Risk | P | I | Score | Priority |
|----|------|---|---|-------|----------|
| R-001 | [Risk 1] | 4 | 5 | 20 | Critical |
| R-002 | [Risk 2] | 3 | 3 | 9 | Medium |
| R-003 | [Risk 3] | 2 | 2 | 4 | Low |
For each significant risk:
After planned mitigations:
Regular review cadence:
## Risk Register: [Project/Initiative]
**Date:** [ISO Date]
**Owner:** [Name]
**Review Cycle:** [Weekly/Monthly]
| ID | Risk Description | Category | P | I | Score | Owner | Response | Actions | Status |
|----|-----------------|----------|---|---|-------|-------|----------|---------|--------|
| R-001 | Key developer may leave during critical phase | Resource | 4 | 5 | 20 | PM | Mitigate | Cross-train, document | Open |
| R-002 | Third-party API may have breaking changes | Technical | 3 | 4 | 12 | Tech Lead | Mitigate | Abstraction layer | Open |
| R-003 | Budget approval may be delayed | Cost | 2 | 4 | 8 | Sponsor | Accept | Monitor | Open |
| R-004 | New regulation may require features | External | 2 | 3 | 6 | BA | Accept | Watch | Open |
### Summary
- **Total Risks:** 4
- **Critical (15+):** 1
- **High (10-14):** 1
- **Medium (5-9):** 1
- **Low (1-4):** 1
quadrantChart
title Risk Assessment Matrix
x-axis Low Impact --> High Impact
y-axis Low Probability --> High Probability
quadrant-1 Critical - Immediate Action
quadrant-2 High - Active Management
quadrant-3 Low - Monitor
quadrant-4 Medium - Plan Response
"R-001 Key Dev": [0.9, 0.8]
"R-002 API Changes": [0.7, 0.6]
"R-003 Budget": [0.7, 0.35]
"R-004 Regulation": [0.5, 0.35]
risk_register:
name: "[Project/Initiative]"
version: "1.0"
date: "2025-01-15"
owner: "Project Manager"
review_cycle: "weekly"
risk_appetite:
overall: "moderate"
schedule: "low"
cost: "moderate"
quality: "low"
scales:
probability:
1: "Rare (<10%)"
2: "Unlikely (10-30%)"
3: "Possible (30-50%)"
4: "Likely (50-70%)"
5: "Almost Certain (>70%)"
impact:
1: "Very Low"
2: "Low"
3: "Medium"
4: "High"
5: "Very High"
risks:
- id: "R-001"
description: "Key developer may leave during critical phase"
category: "Resource"
probability: 4
impact: 5
score: 20
priority: "critical"
owner: "Project Manager"
response_strategy: "mitigate"
response_actions:
- action: "Cross-train team member"
owner: "Tech Lead"
due_date: "2025-02-01"
status: "in_progress"
- action: "Document critical knowledge"
owner: "Developer"
due_date: "2025-02-15"
status: "not_started"
contingency:
trigger: "Developer gives notice"
actions:
- "Accelerate knowledge transfer"
- "Engage contractor"
residual_risk:
probability: 3
impact: 3
score: 9
status: "open"
created_date: "2025-01-15"
last_reviewed: "2025-01-15"
summary:
total: 4
by_priority:
critical: 1
high: 1
medium: 1
low: 1
by_status:
open: 4
mitigated: 0
closed: 0
occurred: 0
## Risk Assessment Summary
**Project:** [Name]
**Date:** [ISO Date]
**Assessed By:** risk-analyst
### Risk Profile
| Priority | Count | Top Risk |
|----------|-------|----------|
| Critical | 1 | Key developer leaving |
| High | 1 | Third-party API changes |
| Medium | 1 | Budget approval delay |
| Low | 1 | Regulatory changes |
### Critical Risks Requiring Action
#### R-001: Key Developer Departure
- **Score:** 20 (P:4 × I:5)
- **Response:** Mitigate through cross-training and documentation
- **Target Residual:** 9 (P:3 × I:3)
- **Actions:** 2 in progress, 0 completed
### Risk Trends
| Metric | This Period | Last Period | Trend |
|--------|-------------|-------------|-------|
| Total Risks | 4 | 3 | ↑ |
| Critical | 1 | 0 | ↑ |
| Closed | 0 | 1 | ↓ |
### Recommendations
1. **Immediate:** Accelerate R-001 mitigation actions
2. **This Week:** Complete API abstraction layer design
3. **Monitor:** Watch for regulatory announcements
| Pitfall | Prevention | |---------|------------| | Vague risk descriptions | Use "condition may cause consequence" format | | Inconsistent scoring | Define and use standard scales | | No risk owners | Assign owner at identification | | Stale register | Schedule regular reviews | | Ignoring opportunities | Include positive risks | | Over-analysis | Focus on high-priority risks | | No contingency | Plan for when risks occur |
swot-pestle-analysis - Strategic threats/opportunitiesroot-cause-analysis - When risks occurdecision-analysis - Risk-based decisionsprioritization - Risk prioritizationdevelopment
Search Milan Jovanovic's .NET blog for Clean Architecture, DDD, CQRS, EF Core, and ASP.NET Core patterns. Use for finding applicable patterns, code examples, and architecture guidance. Invoke when working with .NET projects that could benefit from proven architectural patterns.
tools
Install and configure Data API Builder (DAB) for production SQL Server MCP access with RBAC
tools
Manage MssqlMcp servers - status, rebuild, and upstream updates
tools
Developer environment setup guides for Windows, macOS, Linux, and WSL. Use when setting up development machines, installing tools, configuring environments, or following platform-specific setup guides. Covers package management, shell/terminal, code editors, AI tooling, containerization, databases, and more.